Downtown street work coming to an end
Andrew Edwards
The sound of jackhammers and smell of fresh asphalt filled Downtown
streets often in recent weeks, and now the work is finally winding
down.
Today is scheduled to be the last day of significant work on the
Downtown Rehabilitation Project, Public Works Director Steve May
said.
There is still some touch-up work that needs to be done with the
asphalt in the parking spaces near City Hall, but he said he does not
expect those efforts to delay traffic.
Rough numbers show the project was completed on budget, Project
Manager Derek Wieske said.
Though public works staffers do not have complete figures
available, the work cost about $800,000, which is close to what
planners expected, he said.
The project began in March as construction crews dug into
sidewalks to install new concrete, smooth out the walkways and repair
curbs. Workers also restructured three intersections and repaved
Forest and Ocean avenues and Beach, Mermaid and Second streets.
With the pace of the work slowing down this week, May had only
positive things to say about the project and Sequel Contractors, the
company hired to complete the tasks.
“The contractor executed the work exactly as we planned it,” May
said.
For business owners, the loss of parking spaces and traffic
congestion caused by road closures made the daily grind even tougher.
“It was devastating for our business,” said Ali Javan, owner of
One Hour Photo on Beach Street.
“[Customers] have this perception, there’s no parking Downtown,”
he added.
Ken Lauher, owner of Ken’s Jewelry on Forest Avenue, echoed
Javan’s remarks that scarce parking can put the brakes on commerce.
“It was slow because there wasn’t parking and parking is very
valuable,” Lauher said.
Though merchants were willing to discuss their grievances over the
construction when interviewed, May said that for the most part,
interaction between Downtown business owners and the public works
department went smoothly.
“We got fewer calls ... than any pavement project I’ve ever worked
on,” May said.
Only one business filed a claim against the city seeking
reimbursement for money the business argues it lost as a result of
the project, May said.
The details of claims filed against the city are confidential,
Assistant City Clerk Martha Anderson said.
Apart from the asphalt work near City Hall, planners have not
scheduled any Downtown projects until fall. After the summer festival
season is over, the city will resume work to underground utility
cables in the Downtown area.
That project is expected to happen from September to November, May
said.
All the latest on Orange County from Orange County.
Get our free TimesOC newsletter.
You may occasionally receive promotional content from the Daily Pilot.