Parents concerned about Harbor View’s delay
- Share via
Deirdre Newman
Some parents upset that Harbor View Elementary School will open a
week late have asked that the district move the entire student body
to another school site so they can start on the first day of school.
Parent Dennis Gordon presented the request at an informal meeting
of school district officials, construction representatives and
parents in the corner of Harbor View’s parking lot Wednesday
afternoon. The meeting was punctuated by the sounds of construction
equipment that prompted the meeting in the first place.
District officials announced Tuesday that Harbor View would start
Sept. 8 instead of Sept. 2 because of problems that only became
apparent during renovation. The construction is expected to finish
next week, but officials wanted to make sure teachers had enough time
to set up their classrooms.
While parents expressed frustration with the delay, they are also
concerned about the next two phases of construction, which will start
at the school once classes have begun.
“We are not willing to expose our children to the possibilities of
safety and security issues, or subject them to the dust, dirt, noise
and the tools, equipment and workers as the construction continues
while school is in session,” Gordon said.
District officials stressed that all seven schools now under
construction would remain so during the first few months of school
and that no other parents were asking for their kids to be moved to
another site.
Supt. Robert Barbot said he didn’t feel the situation at Harbor
View warranted moving students at this time.
“Is it perfect? No,” Barbot said. “But [moving] is not good for
the kids. I invite you to look at the data.”
Barbot suggested that a small group of parents work with Asst.
Supt. Susan Despenas to monitor the environment at the school as
construction unfolds.
Harbor View, ensconced in a residential Corona del Mar
neighborhood, is one of seven schools being renovated this year as
part of the Measure A modernization program.
Voters overwhelmingly approved the $110-million Measure A
construction bond in June 2000. The funds have been spread out and
applied to the neediest areas at the schools.
Construction on the first schools began in April, but the bulk of
the work could not be done until the students cleared out in June.
Once the renovation started at Harbor View, work crews discovered
termites, dry rot and higher quantities of asbestos and lead than had
been expected, and so construction has taken longer than expected.
At the meeting, representatives from McCarthy Building Co.
discussed a timeline that calls for the science lab and the computer
lab/library to be open by the end of September. The third and final
phase of construction is expected to end by Dec. 12, said Bonnie
Martin, a project director for McCarthy.
Gordon said if the district did not acquiesce to his request, he
would take it to the school board. Many other parents also adamantly
voiced their desire to have their children moved to another campus.
The district had two student bodies housed on the campus of
Lincoln Elementary School from the fall of 2000 to March of 2001,
during the construction of Newport Coast Elementary School.
Harbor View kindergarten teacher Michele Creason said she was
comfortable with the district’s plans.
“I feel good they delayed [the opening],” she said. “They won’t
open the school unless it’s safe.”
Some students also expressed satisfaction with the delay.
“It’ll be fun because we get an extra week of summer,” said Parker
Varner, 8, who is going into the third grade.
In response to parents’ concerns, district officials are
considering other days to make up for the four lost school days
instead of extending the school year a week.
* DEIRDRE NEWMAN covers Costa Mesa and may be reached at (949)
574-4221 or by e-mail at [email protected].
All the latest on Orange County from Orange County.
Get our free TimesOC newsletter.
You may occasionally receive promotional content from the Daily Pilot.