School’s start will be delayed a week
- Share via
Deirdre Newman
Unexpected problems unearthed while renovating Harbor View Elementary
School will delay the opening of the school by four days.
Instead of the excited patter of students reverberating through
the halls on Sept. 2, when the other district schools open their
doors, Harbor View will be dormant until Sept. 8.
The culprit?
The discovery of termites, dry rot and higher quantities of
asbestos and lead than expected.
Harbor View, ensconced in a residential Corona del Mar
neighborhood, is one of seven schools renovated this year as part of
the Measure A modernization program. It is the only one whose opening
is delayed.
The delay did not occur because the use of jackhammers will
continue during that first week of school, but instead to give
teachers ample time to set up their elaborate learning environments,
said Assistant Supt. Paul Reed. Teachers can’t get into their
classrooms until the construction is done.
“It’s a veritable fairyland teachers create and it takes time,”
Reed said. “It’s not conducive to say on Labor Day, ‘go to it.”
Voters overwhelmingly approved the $110-million Measure A
construction bond in June 2000. The funds have been spread out and
applied to the neediest areas at the schools.
Construction on the first schools broke ground in April, but the
bulk of the work could not be done until the students cleared out in
June.
Harbor View opened in 1953. Reed said the myriad problems plaguing
the elementary school were not discovered until the walls and roofs
were opened. The asbestos was found intact so it did not pose a
health risk to Harbor View students, Reed added.
“It [was] not a health issue until we went in to disturb it,” Reed
said.
Another challenge popped up when the main walkway was torn out to
provide handicapped access. Construction workers found that the
utilities needed to be rerouted because they were only put in one
foot deep instead of six feet, Reed said.
As of late last week, the district was scrambling to open the
school on time, but decided this week to push back the opening until
the following week.
Principal Mellissia Christensen feverishly worked the phones
Tuesday calling all the teachers to let them know. Parents were
notified Tuesday night.
Christensen said she fielded many questions from curious parents
over the past few weeks wondering if the school would be ready on
time.
“It’s not going to surprise a lot of people,” Christensen said of
the delay. “I think [parents] would rather the kids are safe and we
get off to a positive start.”
The next phase of construction at Harbor View will start after the
school year is underway. But the rooms involved will be segmented off
and temporary buildings have already been set up for the students who
will be displaced, Reed said.
Because the students will lose four days at the beginning of the
year, they will most likely be added on at the end of the year, Reed
said.
A meeting will take place at 4 p.m. today at the school to answer
questions and concerns about the delay.
* DEIRDRE NEWMAN covers Costa Mesa and may be reached at (949)
574-4221 or by e-mail at [email protected].