City Hall awaiting finishing touches
Lolita Harper
The unsightly chain-linked fence blocking the entrance and the raw
steel beams that adorn City Hall provide a constant -- and painful --
reminder of a botched project, in which those hired to retrofit the
city’s headquarters simply walked off, leaving an unfinished job.
While the visual focus is on the exterior of the building, inside
City Hall, council members have been putting pressure on city staff
to fix the mess and make sure nothing similar ever happens again.
Bill Morris, the city’s director of public services, met with the
bonding company that guaranteed the completion of the project Monday
to work out details required to get a crew out there to finish the
project. Morris said he hopes to have a resolution in the next week
or so.
“We’ve been working on it; there is just a lot of area to cover,”
Morris said, adding that he knows the City Council and the public are
anxious to see the project completed. “It just takes a little time to
sort everything out.”
City officials said workers from the Anderson White contracting
company simply didn’t show up for work July 1 and have been ducking
any contact with the city since. Morris said the city has tried
unsuccessfully to reach representatives from the Alhambra-based
company.
Anderson White officials could not be reached for comment Monday.
The project, which was already a year behind schedule at the time
of the walk-off, is about 90% complete, Morris said, only lacking in
cosmetic aspects, such as the painting and the patching of holes.
The City Council awarded a $2.8-million contract to Anderson White
in November 2000 for the seismic retrofitting of City Hall and an
additional off-site building. Construction began in January 2001 and
was scheduled to be complete in August 2001. Anderson White had
constant problems performing the work on time and meeting its own
schedules, Morris said.
Council members have been adamant about finishing the project.
Allusions to the retrofitting fiasco were prevalent during seemingly
routine items of City Council business. At last week’s meeting, an
agreement with KFM Engineering for the design of the pavement
reconstruction on 19th Street and Placentia Avenue resulted in a
peppering of questions from Mayor Linda Dixon about the city’s
contracting policies.
Dixon asked if the engineering company had worked with the city
before, if the project was completely on time and if Costa Mesa
officials had properly researched the company’s reputation.
Her concern, she said, was whether Morris and his staff were
actively checking references before awarding city contracts. She
wanted to know if staffers had called other cities to see what type
of work KFM Engineering did for them and whether the company
completed each stage of the process in a timely matter.
“I am upset about the retrofitting and I want to make sure it
doesn’t happen again,” Dixon said.
Councilwoman Libby Cowan was also adamant about when she wanted
the work on City Hall complete: “Now,” she said during the council
meeting.
The building has been in disrepair long enough, Cowan said, and it
is time for city officials to take very aggressive steps to get the
rest of the work finished.
“It has got to be completed,” Cowan said at the Sept. 16 City
Council meeting. “If we are waiting around for some bonding company,
we need to go ahead and do it ourselves.”
Morris said working with the bonding company is really the best
and cheapest course for the city to take. If the city were to
side-step the bonding company and contract the work themselves, they
would have to go through the lengthy bidding process and further
delay the work, he said.
“It is really most expedient for them to come in and do the work
as it was originally bid,” Morris said.
Delays in getting a work crew on site all revolve around money
issues on both sides, Morris said. The bonding company and the city
are trying to save as much money as possible. Attorneys on both sides
are involved and there are detailed issues regarding what work is
left to complete, what work will have to be redone and what the
company will get paid of the remaining contract that had yet to be
paid to Anderson White.
“We want to get everything sorted out so that it gets done and
done correctly so that everybody knows the costs going into it,”
Morris said.
Morris expects another three months of actual work until City Hall
is complete. If everything goes well, the building will be better
than new by the new year, he said.
* LOLITA HARPER covers Costa Mesa. She may be reached at (949)
574-4275 or by e-mail at [email protected].
All the latest on Orange County from Orange County.
Get our free TimesOC newsletter.
You may occasionally receive promotional content from the Daily Pilot.